: A pile is considered "set" if the downward movement does not exceed 10 mm with a minimum holding time of 30 seconds .

: It is recommended to perform the release and re-jack process until two consistent sets are achieved. 4. Quality Control and Potential Issues : A pile is considered "set" if the

These records must be reviewed in real time. If the jacking force exceeds the pile’s structural capacity (e.g., 1.5 times the working load for prestressed concrete), jacking must stop, and an alternative pile section or pre-boring considered. Quality Control and Potential Issues These records must

If refusal occurs above design depth, a load test or restrike (using a drop hammer) is mandatory to confirm capacity. : In areas with complex geology like limestone,